Zhongsha Petrochemical Polypropylene and Low Pressure Equipment Maintenance Plan

Sinopec PE/PP plant is currently driving normally. The original plan for polypropylene and low-voltage equipment was to be overhauled on the 15th. The newly-added maintenance equipment has already arrived at the port for entry. The latest news may be ready for maintenance around 14 days in advance. At that time, the 450,000 tons/year poly-propylene unit and 300,000 tons/year low-voltage unit plan to stop. The current specific maintenance time is uncertain, and it is expected to be around one week. During the maintenance period, the upstream ethylene cracker was operated under reduced load. The current installation of Sinopec is: HP550J from PP plant; 222WT from PE linear plant and PN049-030-122 from low pressure plant.

PHE Spare Gasket For SCHMIDT

Schmidt Bretten Heat Exchanger,Eplacement Schmidt Gaskets,Schmidt Bretten Phe Gasket,Phe Gasket For Schmidt